Jump to content
SAU Community

Recommended Posts

The engineering department would build/design to whatever budget is given to them however it's their responsibility to flag any risks. It's up to the project manager/directors to accept this risk.

Exactly.

And either they did... And then it is ING's management fault.

OR they did not - And they are squarely to blame. If the engineers had a report highlighting the risks etc, it would most likely have been leaked by now. Especially as Work Safe was involved with it all etc etc.

The fact it wasn't leaked or hasn't even been mentioned strongly indicates it was just shitty engineering from the outset... Which is little surprise as that is how things are "done" in recent times because people have NFI what they are doing.

Sorry Pat,

Would have to disagree with you here.

I find it highly unlikely that the engineers built the ferris wheel knowing the risks and that it was due solely to budget. If they knew theithere was a risk in it failing upon being built, I would say that they would have abandoned the project or asked for additional funding.

Moreso that they just stuffed up.

Also their are alot more factors to determine if a project is viable other than payback period. I.e NPV,IRR,and other economic factors such as cash flows, good will and additional interested attracted to the area.

+1

ING would NEVER let a wheel get built that "Will crack in a Melbourne summer" and "It will cost you 4x as much as a result".

It's just retarded. Poor design is certainly the winner here. It's almost sounding like a Gov't project that gets fed to someones "mate" and then costs "blow out unexpectedly"

Sorry Pat,

Would have to disagree with you here.

I find it highly unlikely that the engineers built the ferris wheel knowing the risks and that it was due solely to budget. If they knew theithere was a risk in it failing upon being built, I would say that they would have abandoned the project or asked for additional funding.

Moreso that they just stuffed up.

Also their are alot more factors to determine if a project is viable other than payback period. I.e NPV,IRR,and other economic factors such as cash flows, good will and additional interested attracted to the area.

Yes no doubt there was a stuff up but I wouldnt say its 100% engineers fault. They are contracted/paid to come up with a design that meets the budget of the project. Engineering Dept can show several designs at different costs and risks associated but at the end whoever approved and accepted the risk is at fault.

We dont know.. perhaps at the start of the project they believed the budget was enough to cover. Once you start doing the final design/costing, thats where it adds up and could have blown over budget. With investors promised a return & capital locked, cost would have been cut to squeeze within budget. Most likely the order was given to cut costs, changes were rushed, materials swapped, support beams deleted etc to deliver something which falls close to budget.

If the project manager was guaranteed that it wouldnt fail then I would agree that the Engineering/design team was negligent. If there was a risk, thats where management decide to ask for money or accept the risk...

In the end, its nothing new. Many large ferris wheels built around the world. We know it can be built & material composition, structure & loading isnt complex,

The buck stops with how much money they are willing to spend on building one and whoever thought they can build a ferris wheel for that amount of money in Australia.

Also well aware of IRR, NPV etc when it comes down to capital investment & approval.

Discussion was not tailored towards Chartered Accountants :cheers:

In the end, its nothing new. Many large ferris wheels built around the world. We know it can be built & material composition, structure & loading isnt complex,

So how is it then, that our one has turned into a pile of sh*t?

Poorly designed, poorly constructed.

The buck stops with how much money they are willing to spend on building one and whoever thought they can build a ferris wheel for that amount of money in Australia.

All the money in the world cannot stop shit house design work.

So how is it then, that our one has turned into a pile of sh*t?

Poorly designed, poorly constructed.

Someone had an idea that a ferris wheel can be built for that amount of money.

Either make it happen, or we'll find someone else who will.

Perhaps the engineering firm lied about their design or management accepted the risks.

Time will tell...im saying dont be blaming engineering just yet

All the money in the world cannot stop shit house design work.

Structural engineering; If you want something stronger, then keep adding steel and concrete :nyaanyaa:

This equals more money, so I disagree with your statement...

Australia can design a lot of good things, we just dont have the economy to build here. Hence why companies outsource design work to Australia..

and My ki,

Some manager made the call that we can make a system cheaper than just buying one made.

However after the final details came through, thats where the same manager realised he greatly underquoted.

Nothing to do with Engineering in my opinion. Purely money saving driven, instead of opting for a longer payback period with an existing overseas system.

Guest
This topic is now closed to further replies.



  • Similar Content

  • Latest Posts

    • Ok cool, because I do have some OEM BMW options for light(er) wheels. 17x8.5 M Sport wheels are 11kg and I could put 255's on them. Maybe that's an initial test.
    • So, in the effort of pulling apart airboxes and testing enclosures to see if this aids in MAP loss at WOT I noticed: 1) The ducts up the OEM intercooler holes from the front bar help IAT drastically, whether the pod is shielded from the engine bay by an airbox missing a lid, or an airbox WITH a lid. Plus you get more induction sound without the lid. Having half the airbox (with no lid) acting as a barrier to the headers seems to help. 2) For shits and giggles I checked the TB. This was full pedal travel. This is actually full travel of the TB. Photos aren't perfect, but there was definitely an amount of play in it and it wasn't against the stop. After much swearing and adjusting the pedal, I realised that the cable is actually too long for the skyline pedal travel to fully articulate it. Having the pedal adjusted so WOT was actually hard open on WOT resulted in an idle of 3500rpm. As an aside, this was also the TPS registering at 3.1%. I removed the above to give the pedal enough travel to actually fully open the TB. I now get a satisfying 'thonk' on full open and full closed which you can hear pumping the pedal as it hits the TB stops (with the bonnet open and intake back on). Luckily for me, the screw screws into a raised metal boss under this plastic piece that is now acting as the new throttle stop. I've gained about 20mm (ish) of pedal travel and I can move it maybe a mm or two post open-thonk before it's hard against the stop. After all of this I did a bit of road tuning because a 102MM throttle is sensitive. The difference between holding an 950rpm idle and instantly stalling is about 0.4% of TPS movement. Will that help? I suppose it can't hurt. I set 'closed' point back to where it was, I can definitely feel the extra pedal travel that is needed to actually open the TB fully. But this morning I dropped the car off at Paint Jail again, so who knows when this will re-eventuate out to see if it helps with the top of the dyno hitting a ceiling.
    • Take heart that everyone else seems to have found a way. The OEM S1 indicators do slot in pretty firmly. It may simply be a case of having them sit slightly looser and nobody actually ever noticed this when attempting to remove a indicator from a JSAI bar :p
    • If the original NA ECU has a separate TCU then you are going to need to reroute wires that used to run between the trans and the TCU to the appropriate (1 to 1 equivalent) pins on the ECU. Other than that, it should work. Look up posts by @Kinkstaah on the subject.
    • So the stagea was a series 2 neo det with tiptronic auto. (I have the transmission aswell) and has integrated tcu in the ecu. I'm hoping to use the entire stagea ecu, engine and auto harness. 
×
×
  • Create New...